Emergency LV Switchboard Replacement for a Major Dairy Manufacturing Facility

Outcome

A leading dairy manufacturer restored safe, resilient electrical infrastructure following the emergency replacement of a failed LV switchboard.

Power Testing, a MARCH company, delivered a rapid response solution that restored temporary power, replaced critical infrastructure and returned the site to full operation ahead of schedule, helping minimise production disruption within a 24/7 manufacturing environment.

PDF Download - March
Download

Key Results

  • Emergency site power restored
  • New 3200A LV switchboard installed and commissioned
  • 36-hour shutdown completed in 30 hours
  • Six hours of production time returned to the customer
  • 1.2 million litres per day production capability protected
  • 100% of planned works completed on time
  • Site safely returned to operation

Challenge

A water ingress issue caused flashover damage within the facility’s LV switchboard, leaving the equipment unsafe and beyond repair.

With the site operating a continuous manufacturing process, maintaining power and minimising downtime was critical. A temporary power solution, new switchboard installation and complete cable migration programme all had to be delivered within a tightly controlled shutdown period.

Services Delivered

  • Emergency electrical response
  • Temporary power generation and distribution
  • LV switchboard replacement
  • Cable migration and re-termination
  • Testing and commissioning
  • Electrical isolation management
  • Protection setting verification
  • Project delivery and handover

Case Studies

Asset engineering services for the UK’s best loved cereal brands

Our client is one of the the biggest breakfast cereal and snack producers in the world. For over 40 years, March has provided a range of services to ensure that plants continue to run efficiently including steel and pipework manufacture, mechanical and electrical engineering, systems integration and supporting industry 4.0.

Read more

Cloud Technology Deployment for a Major Utilities Company

When our major water utility client wanted to optimise plant operations and minimise energy consumption it turned to March to support an innovative cloud technology deployment initiative driven by the performance excellence team.

Read more

Systems Integration & Automation for leading food and beverage manufacturer

March has been providing our client, the largest food and beverage company in North America and the second-largest in the world, with Systems Integration and Automation turnkey projects for over 15 years.

Read more

Hybrid facilities management for global food brand

“The health, safety and welfare of our team is more important than all the product in the world! March put health, safety and welfare first in everything they do. An outstanding safety performance from an outstanding company. Well done, March.”

Read more

14% planned production increase per month

March manufacture, install and then integrate all process services for fermentation process at agricultural product production plant.

Read more

+£28m of M&E services for defence organisation

March provide specialist services across five sites for a UK Defence Infrastructure Organisation (DIO)

Read more

MEP for a global aerospace company

March was appointed to provide mechanical, electrical and plumbing engineering projects for a multinational aerospace company.

Read more

Specialist services for a Government defence organisation

March provide specialist services including MEP design and build across numerous projects

Read more

£500,000 PV System Design & Install for the greenest EcoPark in London

March’s customer is a large Recycling Energy Recovery Facility in North London. The facility manages around a quarter of all the rubbish and recycling in London. 

Read more

Condition based monitoring saves £30,000

March were tasked with providing condition based monitoring on their client, a global supplier of food and beverage ingredients, recirculation pumps.

Read more

Reliability improvement saving £425,000

March undertook a reliability improvement project resulting in significant client savings and improvement to the reliability of their critical assets.

Read more

Energy efficiency and carbon savings of 13.67 tonnes

A London Based Science Museum were experiencing efficiency issues with two aged compressors located in separate plant rooms within the site. Upon the breakdown of the GA50 compressor rendering it beyond economical repair, Motivair (a March company) was tasked with providing a quote to replace with a 50Kw replacement.

Read more