March was appointed by their client to deliver a new four-vessel brewhouse for Bath Ales in Warmley.

History

Our client announced ambitious plans to deliver a new brewhouse for Bath Ales in Warmley and engaged with March to design, manufacture and install a state-of-the-art new, four-vessel brewhouse.

Solution

The ‘exam question’ was to provide a modern rapid batch brewery with a high level of automation that would also maintain a quality product. This project demonstrated a market-leading brewery packed with innovations such as efficient cost-saving drives.

One example of innovation on this project was the design and manufacture of flexible hop infusion vessels capable of coping with a wide range of recipes. It was an essential requirement that an in-line operation was achieved that would not affect the turn-around time for the brews.

A bespoke design was provided where the whole hops are retained in a fully flooded vertical cylindrical tank which spreads clarified wort overleaf hops for maximum aroma and pressures the cell to maintain a constant wort level. A conical sieve for hop leaf separation was used and a sealed system with a ‘loop-seal’ and anti-vacuum protection device.

March conducted a feasibility study and produced an initial design. The team reviewed the base recipes for the brewery and built the specification from this information as well as producing a utilisation diagram which ensures the most efficient operation of the Brewery.  This included analysing the brewery workflow along with the available space and establishing an effective workflow from ‘Goods in’ to ‘Beers out’, dealing with waste along the way.

The brewery location presented some challenges; the March team had to work within the constraint of a heavily populated area, ensuring both neighbours and local authorities were not inconvenienced, whilst transforming an Industrial unit into a showpiece brewery.

Results

The delivery of the Brewery was part of a multi-million-pound investment that required March to deliver a sophisticated brewhouse with the capability to produce up to 50,000 brewers’ barrels of beer, the equivalent of approximately 14.5 million pints a year.

This effectively doubled the available brewing capacity.

Case Studies

Asset engineering services for the UK’s best loved cereal brands

Our client is one of the the biggest breakfast cereal and snack producers in the world. For over 40 years, March has provided a range of services to ensure that plants continue to run efficiently including steel and pipework manufacture, mechanical and electrical engineering, systems integration and supporting industry 4.0.

Read more

Cloud Technology Deployment for a Major Utilities Company

When our major water utility client wanted to optimise plant operations and minimise energy consumption it turned to March to support an innovative cloud technology deployment initiative driven by the performance excellence team.

Read more

Systems Integration & Automation for leading food and beverage manufacturer

March has been providing our client, the largest food and beverage company in North America and the second-largest in the world, with Systems Integration and Automation turnkey projects for over 15 years.

Read more

Hybrid facilities management for global food brand

“The health, safety and welfare of our team is more important than all the product in the world! March put health, safety and welfare first in everything they do. An outstanding safety performance from an outstanding company. Well done, March.”

Read more

14% planned production increase per month

March manufacture, install and then integrate all process services for fermentation process at agricultural product production plant.

Read more

+£28m of M&E services for defence organisation

March provide specialist services across five sites for a UK Defence Infrastructure Organisation (DIO)

Read more

Asset care maintenance for global chemical manufacturer

March undertake significant 24 hour asset care for their client, a leading multi billion pound manufacturing company.

Read more

MEP for a global aerospace company

March was appointed to provide mechanical, electrical and plumbing engineering projects for a multinational aerospace company.

Read more