Maintaining Critical High-Voltage Assets for a Major Water Treatment Facility

Outcome

A leading UK water utility successfully completed its four-yearly high-voltage inspection, testing and maintenance programme, ensuring the continued reliability, safety and performance of critical electrical assets across a live operational facility.

Power Testing Ltd (a MARCH company) delivered a comprehensive maintenance and testing programme, helping minimise operational risk, maintain compliance and support uninterrupted service delivery. The project was completed safely, on time and to industry standards.

PDF Download - March
Download

Key Results

  • Four-yearly HV inspection and testing programme completed successfully.
  • 3 transformers maintained.
  • 3 ring main units (RMUs) maintained.
  • 11 protection relays tested.
  • 1 gas circuit breaker maintained.
  • All testing completed to industry standards or better.
  • Works delivered within agreed timescales and deadlines.
  • Minimal disruption to the live operational facility.

Challenge

The customer required specialist high-voltage engineers to carry out statutory four-yearly inspections, testing and maintenance of critical electrical assets within a live operational environment.

The project demanded careful safety planning, management of equipment isolations and coordination with multiple stakeholders to ensure works could be completed safely while minimising disruption to essential operations.

The Solution

Power Testing Ltd (a MARCH company) delivered a planned maintenance and testing programme covering a wide range of high-voltage infrastructure and protection systems.

The scope included:

  • Protection testing.
  • Battery maintenance.
  • General substation maintenance.
  • Oil-insulated transformer inspections.
  • Air-insulated transformer maintenance.
  • Gas circuit breaker maintenance.
  • Cable end box inspections.
  • Ring main unit (RMU) maintenance.
  • LV and primary circuit inspections.

The team managed all safety planning, RAMS documentation, DNO coordination, testing, commissioning and reporting, ensuring safe execution and full compliance throughout the project.

Delivered By

  • High Voltage Engineering
  • Protection Testing
  • Transformer Maintenance
  • Substation Maintenance
  • Testing & Commissioning
  • Project Management

Case Studies

Asset engineering services for the UK’s best loved cereal brands

Our client is one of the the biggest breakfast cereal and snack producers in the world. For over 40 years, March has provided a range of services to ensure that plants continue to run efficiently including steel and pipework manufacture, mechanical and electrical engineering, systems integration and supporting industry 4.0.

Read more

Cloud Technology Deployment for a Major Utilities Company

When our major water utility client wanted to optimise plant operations and minimise energy consumption it turned to March to support an innovative cloud technology deployment initiative driven by the performance excellence team.

Read more

Systems Integration & Automation for leading food and beverage manufacturer

March has been providing our client, the largest food and beverage company in North America and the second-largest in the world, with Systems Integration and Automation turnkey projects for over 15 years.

Read more

Hybrid facilities management for global food brand

“The health, safety and welfare of our team is more important than all the product in the world! March put health, safety and welfare first in everything they do. An outstanding safety performance from an outstanding company. Well done, March.”

Read more

14% planned production increase per month

March manufacture, install and then integrate all process services for fermentation process at agricultural product production plant.

Read more

+£28m of M&E services for defence organisation

March provide specialist services across five sites for a UK Defence Infrastructure Organisation (DIO)

Read more

MEP for a global aerospace company

March was appointed to provide mechanical, electrical and plumbing engineering projects for a multinational aerospace company.

Read more

Specialist services for a Government defence organisation

March provide specialist services including MEP design and build across numerous projects

Read more

£500,000 PV System Design & Install for the greenest EcoPark in London

March’s customer is a large Recycling Energy Recovery Facility in North London. The facility manages around a quarter of all the rubbish and recycling in London. 

Read more

Condition based monitoring saves £30,000

March were tasked with providing condition based monitoring on their client, a global supplier of food and beverage ingredients, recirculation pumps.

Read more

Reliability improvement saving £425,000

March undertook a reliability improvement project resulting in significant client savings and improvement to the reliability of their critical assets.

Read more

Energy efficiency and carbon savings of 13.67 tonnes

A London Based Science Museum were experiencing efficiency issues with two aged compressors located in separate plant rooms within the site. Upon the breakdown of the GA50 compressor rendering it beyond economical repair, Motivair (a March company) was tasked with providing a quote to replace with a 50Kw replacement.

Read more